Lakeview Business District Servicing

About this Project

Recognized as Council's top priority, Lakeview Business District spans more than 600 acres and is set to become a key industrial hub in the metro Edmonton region. Its strategic location near major interprovincial transportation networks and Trade Corridors, along with access to the Edmonton CN intermodal terminal, and proximity to the natural amenities of Big Lake and Lois Hole Centennial Provincial Park, bring assets that enhance its appeal for industrial development. It is adjacent to some of the fastest-growing residential communities in the area, which will greatly benefit employers of the district, positioned for economic growth and set to become a major employment hub anticipated to bring an estimated 5,000 jobs.

The City’s Lakeview Business District Servicing project will extend services into the Lakeview Business District, allowing for a lower cost of entry for developers to develop this area. The services being brought in include transportation, sanitary, storm, and water infrastructure.

Work to Include

The project is anticipated to achieve design and construction of:

  • Range Road 260 realignment and urbanization – from Township Road 540A on the north to Meadowview Drive on the south
  • Meadowview Drive realignment – from Ray Gibbon Drive on east to Range Road 260 on the west
  • Township Road 540A (60% Design Only)
  • Sanitary Sewer Mains, Including a Lift Station
  • Stormwater Mains, Including Stormwater Management Facilities
  • Water Mains

Potential Construction Impacts

To be determined as the design and construction phasing plans progress. Further information anticipated in Q3 2026.

Project Timeline

  • Work completed to date:
    • Project charter & funding approval
    • Consultant procurement
    • Site investigations and preliminary engineering
  • Work ongoing:
    • Detailed design and development of construction phasing plans
    • Land acquisition
    • Environmental permitting
    • External agency approvals
  • Work planned:
    • Completion of detailed design and construction phasing plans
    • Contractor procurement
    • Construction progress

Construction is anticipated to be phased from Q4 2026 to Q4 2030. The phasing plan is currently being developed and is subject to change over the course of the construction schedule. This is based on external influences, which include but are not limited to agency approvals, land acquisition, and development interest in the area.

Other Information

Lakeview Servicing Design Concept Map

Lakeview Business District Website

Interactive Map

Check out the City’s interactive Construction Projects Map that outlines the construction projects planned for this year!

Launch the Map

 