Oakmont Trail
About this Project
The Oakmont Trail seeks to connect the Blais Pedestrian Bridge to Boudreau Road along the north side of the Sturgeon River Valley, through a multi-use trail system. This system connects to the existing trail and will be constructed as a combination of paved multi-use trail, a wooden decked bridge and boardwalk leading to a set of wooden stairs.
Partial Trail Open: The following portions of Oakmont Trail are now open for public use.
- East portion from Blais Bridge to the trail beside 84OUL Orchard Court.
- West portion from Boudreau Road to Riverbank Landing. This section includes stairs.
The closure of the remaining trail section and access to the pedestrian bridge will be constructed in 2027. We thank you for your patience as we work with our partners to complete this work to our trail system.

Work to include:
- Excavation of trail area
- Building of trail structure and pavements
- Construction of concrete abutments for the bridge structure
- Installation of the bridge
- Installation of piles for the boardwalk and stairs
- Construction of the boardwalk and stairs
- Planting of naturalized planting beds and restoration of any areas disturbed by construction activities.
Potential Construction Impacts
Nearby residents can expect some noise from construction activities.
Detours and road closures are not expected; however, residents can expect periods of increased construction-related traffic for the duration of the project.
Project Timeline
Completed
- Construction of the east trail area.
- Plantings and site restoration.
- Construction of the bridge, boardwalk and stairs.
- Construction of the west portion of the trail including plantings and site restoration.
To be completed by others
- The middle portion of the trail connecting the stairs to the pedestrian bridge.
Interactive Map
Check out the City’s interactive Construction Projects Map that outlines the construction projects planned for this year!
Launch the Map