Villeneuve Road
The Project
Villeneuve Road, between Ray Gibbon Drive and St. Albert Trail, is a connector arterial roadway in the City’s transportation network. Upgrading of the existing rural cross-section is underway to deliver an urbanized roadway complete with shared-use paths/sidewalks, streetlighting, underground stormwater and utilities, landscaping and intersection improvements.
Timeline
Construction is being delivered in a phased, multi-year approach, which began in 2022 and is expected to continue through 2029 with gaps in construction years.
For more detailed information on planned or completed phases of this project, visit the Villeneuve Road Urbanization page
Phased Work
- Phase 1: Completed through phased construction, with the bulk of the work occurring in 2022 and 2023. This phase is now under contractor warranty.
- Phase 2A: Construction completed in 2025.
- Phase 2B: Construction is anticipated to begin in mid-May 2026, with completion expected in October 2026. This work will require the closure of Villeneuve Road, between Hogan Road and Dennison Drive/Jensen Gate. For more information, please refer to the Villeneuve Road Urbanization page
Interactive Map
Check out the City’s interactive Construction Projects Map that outlines the construction projects planned for this year!
Launch the Map