Gladstone Crescent Sanitary Sewer Rehabilitation

Project Description

The Sanitary sewer on Gladstone Crescent to Greenwich Crescent was built in 1962. It has been identified through CCTV that the sewer and manholes require rehabilitation through cured-in-place pipe (CIPP) lining. 

CIPP lining will:

  • be installed through existing manhole accesses
  • restore the structural integrity of the sewer for another 50 years
  • enhance the corrosion resistance
  • improve the pipe’s hydraulic capacity
  • reduce potential for odour nuisance

Installation is anticipated to take place at night when the flows in the sewer are lower. 
 

Project Area

Aerial view of Gladstone Crescent outlining the impacted project area

Potential Construction Impacts

During lining operations, residents can anticipate the following potential construction impacts:

  • Local traffic disruptions
  • Possible trail closure
  • Noise from construction equipment
  • Odour from sewer cleaning and lining operations
  • Short-term service disruption (likely at night)

Timeline

Construction is anticipated to take place from August to October 2023.