Hydrant Replacement Program
About the Project
The Fire Hydrant Replacement Program is an annual program that inspects, maintains, and replaces fire hydrants in the city.
Hydrants are in existing neighbourhoods and could be located in or adjacent to sidewalk panels, driveways, boulevards and/or trees.
The City of St Albert has a total of 1,792 fire hydrants.
In 2026, 30 hydrants and valve replacements are anticipated to be replaced.
Work to include:
- Replacement of existing fire hydrants, cathodic protection and hydrant valves
- Site restoration (sod and concrete)
- Landscape maintenance
Locations
Phase 1
| 27 Lambert Cr | 86 lambert Cr |
| 27 Morgan Cr | 3 Hampton Cr |
| 17 Hampton Cr | 25 Marchand Pl |
| 26 Malmo Cr |
PHASE 2
| 39 Lambert Cr | 30 Lambert Cr |
| 140 Mission Ave | 41 Berrymore Dr |
| 7 Morgan Cr | 9 Harriot Ct |
| 28 Bocock Pl | 5 Heath Pl |
| 40 Beaverbrook | 49 Hamilton Cr |
| 25 Chisolm Ave | 22 Beaverbrook Cr |
| 31 Everest Cr | 5 Atkinson Pl |
| 220 Chatelain Dr | 12 Leblanc Pl |
| 245 Carnegie Dr | R.B.C Hydrant on Bellerose |
| 18 Bocock Pl | 13 Elliot Pl |
| 157 Larose |
Potential Construction Impacts
Construction is anticipated to impact the boulevard, driveway and sidewalk.
- Limited on-street parking.
- Portions of the sidewalks, boulevard and roadways will be temporarily closed.
- Open excavation. Please obey all signage and fenced-off areas.
- Equipment will be on-site for excavation and materials installation.
- Temporary Water Disruption
- Noise disturbance will occur during work hours.
Timeline
- May to October 2026
Interactive Map
Check out the City’s interactive Construction Projects Map that outlines the construction projects planned for this year!