About the Project
As of 2024, approximately 22,000 sanitary sewer services are connected to the City of St. Albert wastewater collection system. Predominately all services installed prior to 1980 consist of either concrete, clay tile or no-corrode.
Over the past decade, the City has conducted a proactive repair, maintain or replacement (RMR) program of aged, deteriorated or deficient service lines of the City portion (from mainline to property line) of household sanitary sewer services.
The Utilities branch normally performs over 1,200 sanitary sewer inspections annually as part of its in-home maintenance service. This program captures CCTV inspection and rating of the current condition/state of the entire sanitary sewer service from point of entry within the home to the City wastewater main to determine if either scheduled maintenance is sufficient in upholding a reasonable state of sewer service reliability or if the sewer service is deemed applicable for repair, replacement or relining.
Work to include:
- CCTV pre-inspection to be completed to confirm location and limits of repair
- Replacement of existing sewer service line
- CCTV post inspection
- Site restoration (sod and concrete)
- Landscape maintenance where required
Locations
37 Ellington Crescent | 15 Edward Place |
8 Oakridge Dr N | 7 Oxford Place |
8 Donlevy Place | 68 Durocher Place |
218 North Ridge Drive | 51 Nevis Close |
16 Leveque Way | 11 Lamartine Crescent |
15 Fairfax Crescent | 25 Fleetwood Crescent |
47 Swallow Crescent | 22 Huntington Crescent |
Potential Construction Impacts
Construction is anticipated to impact the boulevard, driveway, roadway and/or sidewalk. The following is an outline of potential construction impacts:
- Limited on-street parking.
- Limited driveway parking.
- Portions of the sidewalks, boulevard and roadways will be temporarily closed.
- Open excavation. Please obey all signage and fenced-off areas.
- Equipment will be on-site for excavation and materials installation.
- Noise disturbance will occur during work hours.
Timeline
- May to September 2024